AGC and E.ON sign first green PPA in France

Partners AGC and E.ON signed the first green Power Purchase Agreement (PPA) in France to improve energy efficiency and decarbonisation.

The joint project will tackle waste heat recovery and production of green power at AGC‘s float glass plant in Seingbouse, France.

The project will be developed, implemented, financed and operated by E.ON and supported by the French Government as part of the ‘France Relance’ plan set up by ADEME (French Environment and Energy Management Agency).

Both parties have agreed to structure the project as PPA where E.ON will produce and sell electricity to AGC on a long-term basis at fixed price. This will allow AGC’s site to become largely independent of volatile energy markets.

At AGC's Seingbouse site, heat will be recovered to generate CO2-neutral electricity by implementing an innovative Organic Rankine Cycle (ORC) plant with a capacity of 1.3 megawatts (MW).

To further decarbonise, E.ON is also installing a photovoltaic power plant with a capacity of 2.7 MW on the factory’s premises. It will generate renewable electricity on a total of 27 000 m2.

By combining the photovoltaic panels with the ORC power plant, E.ON will annually provide AGC with around 10 gigawatt hours (GWh) of decarbonised electricity from 2023 onwards.

This electricity is fully produced and consumed on AGC’s site and covers a large part of the electricity needs. On this basis, around 595 tons of CO2 are annually avoided.

Marc Bartheld, Plant Manager AGC Seingbouse, said: "Our plant is one of AGC’s larger production lines for the building sector with a yearly production of 240,000 tons of float glass. Our goal is to reduce our greenhouse gas emissions by 30% and our energy consumption by 20% by 2030.

“To achieve this, we are constantly working to improve the environmental performance of our production sites. The project in Seingbouse here in France is a perfect example of how E.ON can help us to not only achieve our sustainability goals, but also to secure the site's long-term competitiveness."

E.ON and AGC Glass Europe launched their partnership back in 2019 and have already implemented several energy efficiency projects in throughout Europe. In addition, the construction of further photovoltaic plants with up to 20 megawatts capacity is planned in Hungary and the Czech Republic.

28.04.2022, AGC

此网站新闻材料的版权属于公司或第三方的新闻提供者,其所有权利保留。所有新闻材料对其访问者只能限于其本人使用,并且使用此材料的风险由其使用者独自自行承担。严禁对新闻材料进行再次发布和其它商业利用. 作为商业贸易的用途。如果新闻材料由第三方提供,当应用此新闻材料时,每个使用者都同意遵守,并且受此特定的项目的约束。Glass Global并不代表及认可新闻材料中所包含的内容及新闻中的外部网站的内容的准确性及可靠性。

Should the content or the design of these sites violate third parties rights or legal prescriptions, we kindly ask you to send us a respective message without invoice or cost. We guarantee that passages where the claim is considered as justified will be removed immediately, without any necessity to involve any lawyer into this issue. We will reject any claim caused by submission of a honorary note in this regard without any prior contact and confirmation of the issueby us and we reserve the right ssue counter claim ourselves because of violation of aforesaid conditions.